Assessment Year | 2023 |
---|---|
Principal Product | Treated Wastewater |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $5 M to 10M |
# of Employees | 6 |
Plant Area |
380,000
ft2
|
Annual Production | 1,123,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Louisiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $221,100 | 3,654,560 |
kWh
|
$0.060 | |
Electricity Demand | $15,227 | 6,091 |
kW-mo/yr
|
$2.50 | |
Electricity Fees | $87 | - |
|
- | |
Waste Disposal Costs | |||||
Water Usage | $52,377 | 37,955 |
Tgal
|
$1.38 | |
TOTAL YEARLY COSTS | $288,791 | ||||
RECOMMENDED SAVINGS* | $64,337 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $10,344 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Usage Savings |
---|---|---|---|---|---|---|---|
01 | 3.4113: Treat and reuse rinse waters | $53,474 | $5,948 |
$1,186
(-19,597)
kWh
|
- |
$52,288
-
Tgal
|
|
02 | 2.6231: Utilize controls to operate equipment only when needed | $2,629 | $335,972 |
$2,460
40,657
kWh
|
$169
-
kW-mo/yr
|
- | |
03 | 2.7111: Reduce illumination to minimum necessary levels | $7,506 | $3,722 |
$7,023
116,076
kWh
|
$484
-
kW-mo/yr
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $209 | $343 |
$209
3,446
kWh
|
- | - | |
05 | 2.7135: Install occupancy sensors | $519 | $332 |
$519
8,580
kWh
|
- | - | |
TOTAL RECOMMENDED | $64,337 | $346,317 |
$11,396
149,163
kWh
|
$653
-
kW-mo/yr
|
$52,288
-
Tgal
|
||
TOTAL IMPLEMENTED | $10,344 | $340,038 |
$9,691
160,179
kWh
|
$653
-
kW-mo/yr
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs