ITAC Assessment: LT0142
ITAC logo
ITAC Assessment: LT0142
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product RUBBERIZED FUEL TANKS
NAICS
n/a
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 490
Plant Area
n/a
Annual Production 5,000
pieces
Production Hrs. Annual 2,496
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $457,741 7,060,082
kWh
Natural Gas $238,139 77,164
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $236,961 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $18,728

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 3.6192: Use a less expensive method of waste removal $214,983 $77,904 - $16,695
-
MMBtu
$198,288
02 2.1233: Analyze flue gas for proper air/fuel ratio $7,542 $442 - $8,142
-
MMBtu
$(-600.0)
03 2.1233: Analyze flue gas for proper air/fuel ratio $2,008 $442 - $2,008
-
MMBtu
-
04 2.2414: Use waste heat from hot flue gases to preheat $2,470 $400 - $2,470
-
MMBtu
-
05 2.7261: Install timers and/or thermostats $3,092 $200 $2,555
52,755
kWh
$537
-
MMBtu
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $3,250 $754 $3,250
55,393
kWh
- -
07 2.2136: Install / repair insulation on steam lines $423 $100 - $423
-
MMBtu
-
08 2.2135: Repair and eliminate steam leaks $3,193 $224 - $3,193
-
MMBtu
-
TOTAL RECOMMENDED $236,961 $80,466 $5,805
108,148
kWh
$33,468
-
MMBtu
$197,688
TOTAL IMPLEMENTED $18,728 $1,808 $2,555
52,755
kWh
$16,773
-
MMBtu
$(-600.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs