ITAC Assessment: LT0135
ITAC logo
ITAC Assessment: LT0135
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product FLUID MILK, FRUIT DRINKS
NAICS
n/a
SIC 2026: Fluid Milk
Sales Range $10
M
to 50
M
# of Employees 50
Plant Area
n/a
Annual Production 11,000
Tgal
Production Hrs. Annual 3,640
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $158,248 2,842,028
kWh
Natural Gas $39,000 9,822
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $10,999 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $860 - - $1,460
-
MMBtu
$(-600.0)
02 2.1131: Repair faulty insulation in furnaces, boilers, etc $457 $275 - $457
-
MMBtu
-
03 2.2511: Insulate bare equipment $551 $1,354 $316
6,155
kWh
$235
-
MMBtu
-
04 2.2614: Use cooling tower or economizer to replace chiller cooling $2,470 - $2,470
60,961
kWh
- -
05 2.2136: Install / repair insulation on steam lines $715 $146 - $715
-
MMBtu
-
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $402 - $402
9,965
kWh
- -
07 2.4133: Use most efficient type of electric motors $226 $571 $226
50,117
kWh
- -
08 2.4111: Utilize energy-efficient belts and other improved mechanisms $383 - $383
6,741
kWh
- -
09 2.7261: Install timers and/or thermostats $529 $129 $393
9,672
kWh
$136
-
MMBtu
-
10 2.7111: Reduce illumination to minimum necessary levels $640 $770 $640
15,826
kWh
- -
11 2.7142: Utilize higher efficiency lamps and/or ballasts $121 $85 $139
2,931
kWh
- $(-18.0)
12 2.7142: Utilize higher efficiency lamps and/or ballasts $3,312 $3,363 $2,505
61,841
kWh
- $807
13 2.2441: Preheat boiler makeup water with waste process heat $333 $1,770 - $333
-
MMBtu
-
TOTAL RECOMMENDED $10,999 $8,463 $7,474
224,209
kWh
$3,336
-
MMBtu
$189
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs