ITAC Assessment: LT0132
ITAC logo
ITAC Assessment: LT0132
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product RUBBER ROLL COVERINGS
NAICS
n/a
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 28
Plant Area
n/a
Annual Production 420,000
lb
Production Hrs. Annual 7,344
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $67,098 1,215,123
kWh
Natural Gas $37,960 8,992
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $31,158 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,076

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.2511: Insulate bare equipment $1,820 $1,967 - $1,820
-
MMBtu
-
02 2.5194: Redesign process $23,180 $3,057 $1,230
26,671
kWh
$18,200
-
MMBtu
$3,750
03 2.4133: Use most efficient type of electric motors $352 $855 $352
6,448
kWh
- -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $256 $300 $256
4,689
kWh
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $50 $120 $50
1,465
kWh
- -
06 2.7261: Install timers and/or thermostats $1,500 $150 $1,500
29,894
kWh
- -
07 2.2437: Recover waste heat from equipment $4,000 $3,680 - $4,000
-
MMBtu
-
TOTAL RECOMMENDED $31,158 $10,129 $3,388
69,167
kWh
$24,020
-
MMBtu
$3,750
TOTAL IMPLEMENTED $2,076 $2,267 $256
4,689
kWh
$1,820
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs