ITAC Assessment: OD0081
ITAC logo
ITAC Assessment: OD0081
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Ribbon
NAICS
n/a
SIC 2396: Automotive Trimmings, Apparel Findings, and Related Products
Sales Range $5
M
to 10
M
# of Employees 80
Plant Area 28,000
ft2
Annual Production 9,000,000
thousand feet
Production Hrs. Annual 2,125
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $15,883 310,082
kWh
Electricity Demand $5,946 1,058
kW-mo/yr
Electricity Fees $2,981 -
Natural Gas $11,543 1,747
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $759,385 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings By-product Production Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,491 $5,176 n/a $949
18,464
kWh
$1,542
-
kW-mo/yr
- - - - - -
02 2.6214: Shut off pilots in standby equipment $222 - n/a - - $222
-
MMBtu
- - - - -
03 3.5212: Regrind, reuse, or sell scrap plastic parts $485 - n/a - - - $485
-
lb
- - - -
04 3.1181: Eliminate a by-product $204,312 $6,350 n/a - - - - - $54,312 - $150,000
05 4.322: Eliminate old stock and modify inventory control $551,875 $51,389 n/a - - - - $15,625 - $536,250 -
TOTAL RECOMMENDED $759,385 $62,915 $949
18,464
kWh
$1,542
-
kW-mo/yr
$222
-
MMBtu
$485
-
lb
$15,625 $54,312 $536,250 $150,000
TOTAL IMPLEMENTED - - - - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs