Assessment Year | 2011 |
---|---|
Principal Product | Asphalt |
NAICS | 324122: Asphalt Shingle and Coating Materials Manufacturing |
SIC | 2952: Asphalt Felts and Coatings |
Sales Range | $10 M to 50M |
# of Employees | 20 |
Plant Area |
76,000
ft2
|
Annual Production | 140,000
lb
|
Production Hrs. Annual | 8,376
hrs
|
Location (State) | Minnesota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $504,333 | 9,603,476 |
kWh
|
$0.053 |
Electricity Demand | $160,732 | 18,192 |
kW-mo/yr
|
$8.84 |
Natural Gas | $674,936 | 130,583 |
MMBtu
|
$5.17 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $33,083 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,185 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,826 | $2,900 |
$2,294
43,680
kWh
|
$532
-
kW-mo/yr
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $509 | $522 |
$413
7,862
kWh
|
$96
-
kW-mo/yr
|
- | |
03 | 2.7135: Install occupancy sensors | $2,107 | $840 |
$2,107
40,137
kWh
|
- | - | |
04 | 2.4133: Use most efficient type of electric motors | $880 | $1,922 |
$715
13,613
kWh
|
$165
-
kW-mo/yr
|
- | |
05 | 2.4221: Install compressor air intakes in coolest locations | $105 | $300 |
$77
1,459
kWh
|
$28
-
kW-mo/yr
|
- | |
06 | 2.2515: Use optimum thickness insulation | $16,511 | $17,910 | - | - |
$16,511
-
MMBtu
|
|
07 | 2.2136: Install / repair insulation on steam lines | $280 | $383 | - | - |
$280
-
MMBtu
|
|
08 | 2.1213: Direct warmest air to combustion intake | $9,865 | $1,500 | - | - |
$9,865
-
MMBtu
|
|
TOTAL RECOMMENDED | $33,083 | $26,277 |
$5,606
106,751
kWh
|
$821
-
kW-mo/yr
|
$26,656
-
MMBtu
|
||
TOTAL IMPLEMENTED | $14,185 | $7,144 |
$3,499
66,614
kWh
|
$821
-
kW-mo/yr
|
$9,865
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs