ITAC Assessment: IA0469
ITAC logo
ITAC Assessment: IA0469
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Asphalt
NAICS 324122: Asphalt Shingle and Coating Materials Manufacturing
SIC 2952: Asphalt Felts and Coatings
Sales Range $10
M
to 50
M
# of Employees 20
Plant Area 76,000
ft2
Annual Production 140,000
lb
Production Hrs. Annual 8,376
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $504,333 9,603,476
kWh
Electricity Demand $160,732 18,192
kW-mo/yr
Natural Gas $674,936 130,583
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $33,083 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $14,185

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,826 $2,900 $2,294
43,680
kWh
$532
-
kW-mo/yr
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $509 $522 $413
7,862
kWh
$96
-
kW-mo/yr
-
03 2.7135: Install occupancy sensors $2,107 $840 $2,107
40,137
kWh
- -
04 2.4133: Use most efficient type of electric motors $880 $1,922 $715
13,613
kWh
$165
-
kW-mo/yr
-
05 2.4221: Install compressor air intakes in coolest locations $105 $300 $77
1,459
kWh
$28
-
kW-mo/yr
-
06 2.2515: Use optimum thickness insulation $16,511 $17,910 - - $16,511
-
MMBtu
07 2.2136: Install / repair insulation on steam lines $280 $383 - - $280
-
MMBtu
08 2.1213: Direct warmest air to combustion intake $9,865 $1,500 - - $9,865
-
MMBtu
TOTAL RECOMMENDED $33,083 $26,277 $5,606
106,751
kWh
$821
-
kW-mo/yr
$26,656
-
MMBtu
TOTAL IMPLEMENTED $14,185 $7,144 $3,499
66,614
kWh
$821
-
kW-mo/yr
$9,865
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs