Assessment Year | 1994 |
---|---|
Principal Product | Finished Leather |
NAICS |
n/a
|
SIC | 2386: Leather and Sheep-Lined Clothing |
Sales Range | $1 M to 5M |
# of Employees | 100 |
Plant Area |
30,000
ft2
|
Annual Production | 3,000
thousand feet
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Maine |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $137,310 | 1,671,747 |
kWh
|
$0.082 |
Fuel Oil #6 | $57,490 | 21,842 |
MMBtu
|
$2.63 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $10,124 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,124 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $1,570 | $4,500 |
$1,570
-
kWh
|
- | - | |
02 | 2.1213: Direct warmest air to combustion intake | $446 | $450 | - |
$446
-
MMBtu
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,124 | $800 |
$1,124
13,775
kWh
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,005 | $14,689 |
$5,005
60,961
kWh
|
- | - | |
05 | 2.8123: Pay utility bills on time | $1,979 | - | - | - | $1,979 | |
TOTAL RECOMMENDED | $10,124 | $20,439 |
$7,699
74,736
kWh
|
$446
-
MMBtu
|
$1,979 | ||
TOTAL IMPLEMENTED | $1,124 | $800 |
$1,124
13,775
kWh
|
- | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs