ITAC Assessment: DS0048
ITAC logo
ITAC Assessment: DS0048
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Grey and Ductile Iron Castings
NAICS
n/a
SIC 3321: Gray and Ductile Iron Foundries
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 109,531
ft2
Annual Production 10,562
ton
Production Hrs. Annual 6,864
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $757,434 24,774,912
kWh
Electricity Demand $254,745 65,172
kW-mo/yr
Electricity Fees $81,839 -
Natural Gas $197,021 84,226
MMBtu
LPG $32,366 6,713
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $110,709 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $25,943

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.3212: Optimize plant power factor $1,037 $1,900 - - $1,037 - - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $7,486 $18,021 $6,078
198,710
kWh
$1,408
-
kW-mo/yr
- - - - -
03 2.4133: Use most efficient type of electric motors $5,919 $18,845 $4,181
136,870
kWh
$1,738
-
kW-mo/yr
- - - - -
04 2.4221: Install compressor air intakes in coolest locations $5,971 $750 $5,971
195,193
kWh
- - - - - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,128 $250 $1,128
36,928
kWh
- - - - - -
06 2.2511: Insulate bare equipment $4,640 $3,678 - - - $4,640
-
MMBtu
- - -
07 2.2437: Recover waste heat from equipment $5,733 $6,500 - - - $5,733
-
MMBtu
- - -
08 3.4156: Use flow control valves on equipment to optimize water use $26,694 $160 - - - - $26,694
-
Tgal
- -
09 3.4114: Replace city water with recycled water via cooling tower $34,241 $40,760 $(-34.0)
(-879)
kWh
- - - $35,775
-
Tgal
- $(-1,500.0)
10 3.4116: Meter recycled water (to reduce sewer charges) $14,032 $1,350 - - - - $14,032
-
Tgal
- -
11 3.5315: Lease / purchase baler; sell cardboard to recycler $3,828 $4,750 - - - - - $3,828
-
lb
-
TOTAL RECOMMENDED $110,709 $96,964 $17,324
566,822
kWh
$3,146
-
kW-mo/yr
$1,037 $10,373
-
MMBtu
$76,501
-
Tgal
$3,828
-
lb
$(-1,500.0)
TOTAL IMPLEMENTED $25,943 $49,194 $11,387
372,508
kWh
$3,146
-
kW-mo/yr
$1,037 $10,373
-
MMBtu
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs