ITAC Assessment: LS1907
ITAC logo
ITAC Assessment: LS1907
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Polypropylene
NAICS 325211: Plastics Material and Resin Manufacturing
SIC 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers
Sales Range $500
k
to 1
M
# of Employees 6
Plant Area 25,000
ft2
Annual Production 780,000
pieces
Production Hrs. Annual 4,160
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $75,942 954,072
kWh
Electricity Demand $61,701 4,710
kW-mo/yr
Waste Disposal Costs
Water Usage $790 425
Tgal
TOTAL YEARLY COSTS $138,433
RECOMMENDED SAVINGS* $21,755 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $302 $50 $302
3,790
kWh
-
02 2.7124: Make a practice of turning off lights when not needed $1,921 $500 $1,921
24,018
kWh
-
03 2.6231: Utilize controls to operate equipment only when needed $180 $75 $180
2,245
kWh
-
04 3.7312: Implement a regular maintenance program to reduce emissions from leaky valves and pipe fittings $305 $180 $305
3,827
kWh
-
05 2.6218: Turn off equipment when not in use $40 $25 $40
504
kWh
-
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $8,396 $6,225 $8,396
105,481
kWh
-
07 2.7447: Install vinyl strip / high speed / air curtain doors $179 $135 $179
2,242
kWh
-
08 2.7142: Utilize higher efficiency lamps and/or ballasts $10,362 $10,917 $7,038
87,971
kWh
$3,324
-
kW-mo/yr
09 2.4111: Utilize energy-efficient belts and other improved mechanisms $70 $205 $70
885
kWh
-
TOTAL RECOMMENDED $21,755 $18,312 $18,431
230,963
kWh
$3,324
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs