Assessment Year | 1988 |
---|---|
Principal Product | LEAD ACID BATTERIES |
NAICS |
n/a
|
SIC | 3691: Storage Batteries |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
n/a
|
Annual Production | 1,400,000
pieces
|
Production Hrs. Annual | 4,312
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $629,985 | 10,631,008 |
kWh
|
$0.059 |
Natural Gas | $249,096 | 48,640 |
MMBtu
|
$5.12 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $95,424 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $95,424 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.2514: Cover open tanks | $64,900 | $12,000 |
$49,000
1,058,030
kWh
|
$15,900
-
MMBtu
|
- | |
02 | 2.2515: Use optimum thickness insulation | $9,378 | $2,760 |
$5,292
114,302
kWh
|
$4,086
-
MMBtu
|
- | |
03 | 2.5194: Redesign process | $6,995 | - |
$6,160
133,353
kWh
|
$835
-
MMBtu
|
- | |
04 | 2.2211: Use optimum temperature | $3,576 | - |
$2,900
62,720
kWh
|
$676
-
MMBtu
|
- | |
05 | 2.4133: Use most efficient type of electric motors | $2,660 | $2,693 |
$2,660
49,824
kWh
|
- | - | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,640 | - |
$4,640
89,097
kWh
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,049 | $453 |
$2,260
42,497
kWh
|
- | $(-211.0) | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $247 | $55 |
$261
4,982
kWh
|
- | $(-14.0) | |
09 | 2.7261: Install timers and/or thermostats | $979 | $1,050 |
$568
12,309
kWh
|
$411
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $95,424 | $19,011 |
$73,741
1,567,114
kWh
|
$21,908
-
MMBtu
|
$(-225.0) | ||
TOTAL IMPLEMENTED | $95,424 | $19,011 |
$73,741
1,567,114
kWh
|
$21,908
-
MMBtu
|
$(-225.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs