ITAC Assessment: LT0090
ITAC logo
ITAC Assessment: LT0090
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product ASPHALT HOT MIX
NAICS
n/a
SIC 2951: Asphalt Paving Mixtures and Blocks
Sales Range $5
M
to 10
M
# of Employees 55
Plant Area
n/a
Annual Production 175,000
ton
Production Hrs. Annual 1,600
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $39,936 261,137
kWh
Natural Gas $214,613 55,895
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $10,362 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,002

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2511: Insulate bare equipment $782 $146 - $782
-
MMBtu
02 2.4133: Use most efficient type of electric motors $360 $927 $360
3,810
kWh
-
03 2.7261: Install timers and/or thermostats $420 - $420
6,448
kWh
-
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $8,800 - $11,500
174,091
kWh
$(-2,700.0)
-
MMBtu
TOTAL RECOMMENDED $10,362 $1,073 $12,280
184,349
kWh
$(-1,918.0)
-
MMBtu
TOTAL IMPLEMENTED $10,002 $146 $11,920
180,539
kWh
$(-1,918.0)
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs