ITAC Assessment: LT0059
ITAC logo
ITAC Assessment: LT0059
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product ROLLS, BREAD, MUFFINS
NAICS
n/a
SIC 2051: Bread and Other Bakery Products, Except Cookies and Crackers
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area
n/a
Annual Production 57,000,000
lb
Production Hrs. Annual 5,720
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $332,548 5,266,999
kWh
Natural Gas $200,824 49,306
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,308 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,208

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.6232: Install set-back timers $1,810 $260 $1,810
43,669
kWh
-
02 2.2443: Re-use or recycle hot or cold process exhaust air $1,100 $4,260 - $1,100
-
MMBtu
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $657 $85 $657
12,896
kWh
-
04 2.7422: Plant trees or shrubs near windows to shield from sunlight $741 $1,440 $741
17,878
kWh
-
TOTAL RECOMMENDED $4,308 $6,045 $3,208
74,443
kWh
$1,100
-
MMBtu
TOTAL IMPLEMENTED $3,208 $1,785 $3,208
74,443
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs