ITAC Assessment: LT0057
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product CERAMIC SEALS
NAICS
n/a
SIC 3053: Gaskets, Packing, and Sealing Devices
Sales Range $5
M
to 10
M
# of Employees 101
Plant Area
n/a
Annual Production 2,000,000
pieces
Production Hrs. Annual 4,352
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $102,782 1,398,886
kWh
Natural Gas $70,506 17,291
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $9,942 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,829

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2414: Use waste heat from hot flue gases to preheat $7,100 $2,130 - $7,100
-
MMBtu
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $775 $216 $775
12,309
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,054 $527 $1,054
17,585
kWh
-
04 2.7261: Install timers and/or thermostats $1,013 $1,350 $1,013
29,308
kWh
-
TOTAL RECOMMENDED $9,942 $4,223 $2,842
59,202
kWh
$7,100
-
MMBtu
TOTAL IMPLEMENTED $1,829 $743 $1,829
29,894
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs