ITAC Assessment: LT0056
ITAC logo
ITAC Assessment: LT0056
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product PAPER BAGS
NAICS
n/a
SIC 2674: Uncoated Paper and Multiwall Bags
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area
n/a
Annual Production 18,000
ton
Production Hrs. Annual 6,864
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $62,386 1,225,967
kWh
Natural Gas $36,002 8,778
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $2,168 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,094

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $201 $300 - $201
-
MMBtu
02 2.6214: Shut off pilots in standby equipment $74 $130 - $74
-
MMBtu
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $787 $197 $787
13,189
kWh
-
04 2.4221: Install compressor air intakes in coolest locations $231 $160 $231
9,672
kWh
-
05 2.4133: Use most efficient type of electric motors $232 $225 $232
4,982
kWh
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $643 $84 $643
13,775
kWh
-
TOTAL RECOMMENDED $2,168 $1,096 $1,893
41,618
kWh
$275
-
MMBtu
TOTAL IMPLEMENTED $2,094 $966 $1,893
41,618
kWh
$201
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs