| Assessment Year | 2008 |
|---|---|
| Principal Product | Ceramic Plating |
| NAICS | 315990: Apparel Accessories and Other Apparel Manufacturing |
| SIC | 3299: Nonmetallic Mineral Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 60 |
| Plant Area |
60,000
ft2
|
| Annual Production | 486,000
lb
|
| Production Hrs. Annual | 4,400
hrs
|
| Location (State) | Delaware |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $614,509 | 7,000,548 |
kWh
|
$0.088 |
| Electricity Demand | $70,754 | 16,724 |
kW-mo/yr
|
$4.23 |
| Natural Gas | $17,674 | 1,607 |
MMBtu
|
$11.00 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $83,690 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.6218: Turn off equipment when not in use | $26,000 | - |
$26,000
260,000
kWh
|
- | |
| 02 | 2.8113: Purchase gas directly from a contract gas supplier | $8,300 | - | - |
$8,300
-
MMBtu
|
|
| 03 | 2.6218: Turn off equipment when not in use | $6,900 | - |
$6,900
69,000
kWh
|
- | |
| 04 | 2.1117: Relocate oven / furnace to more efficient location | $31,000 | $26,000 |
$53,000
530,000
kWh
|
$(-22,000.0)
-
MMBtu
|
|
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,500 | $22,600 |
$9,500
95,000
kWh
|
- | |
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,400 | $500 |
$1,400
14,000
kWh
|
- | |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $590 | $150 |
$590
5,700
kWh
|
- | |
| TOTAL RECOMMENDED | $83,690 | $49,250 |
$97,390
973,700
kWh
|
$(-13,700.0)
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs