ITAC Assessment: DL0023
ITAC logo
ITAC Assessment: DL0023
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Ceramic Plating
NAICS 315990: Apparel Accessories and Other Apparel Manufacturing
SIC 3299: Nonmetallic Mineral Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 60
Plant Area 60,000
ft2
Annual Production 486,000
lb
Production Hrs. Annual 4,400
hrs
Location (State) Delaware

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $614,509 7,000,548
kWh
Electricity Demand $70,754 16,724
kW-mo/yr
Natural Gas $17,674 1,607
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $83,690 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.6218: Turn off equipment when not in use $26,000 - $26,000
260,000
kWh
-
02 2.8113: Purchase gas directly from a contract gas supplier $8,300 - - $8,300
-
MMBtu
03 2.6218: Turn off equipment when not in use $6,900 - $6,900
69,000
kWh
-
04 2.1117: Relocate oven / furnace to more efficient location $31,000 $26,000 $53,000
530,000
kWh
$(-22,000.0)
-
MMBtu
05 2.7142: Utilize higher efficiency lamps and/or ballasts $9,500 $22,600 $9,500
95,000
kWh
-
06 2.4231: Reduce the pressure of compressed air to the minimum required $1,400 $500 $1,400
14,000
kWh
-
07 2.4221: Install compressor air intakes in coolest locations $590 $150 $590
5,700
kWh
-
TOTAL RECOMMENDED $83,690 $49,250 $97,390
973,700
kWh
$(-13,700.0)
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs