| Assessment Year | 2026 |
|---|---|
| Principal Product | Water Screens |
| NAICS | 333120: Construction Machinery Manufacturing |
| SIC | 3533: Oil and Gas Field Machinery and Equipment |
| Sales Range | $10 M to 50M |
| # of Employees | 114 |
| Plant Area |
145,643
ft2
|
| Annual Production | 40
units
|
| Production Hrs. Annual | 2,340
hrs
|
| Location (State) | Louisiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $124,731 | 1,088,314 |
kWh
|
$0.11 |
| Electricity Demand | $25,120 | 7,028 |
kW-mo/yr
|
$3.57 |
| LPG | $8,415 | 360 |
MMBtu
|
$23.38 |
| TOTAL YEARLY COSTS | $158,266 | |||
| RECOMMENDED SAVINGS* | $90,513 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | LPG Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,280 | $25 |
$1,280
11,129
kWh
|
- | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $365 | $45 |
$365
3,176
kWh
|
- | - | |
| 03 | 2.7211: Clean and maintain refrigerant condensers and towers | $1,247 | $490 |
$1,247
10,844
kWh
|
- | - | |
| 04 | 2.8117: Install sub-metering equipment | $6,258 | $5,250 |
$6,258
54,416
kWh
|
- | - | |
| 05 | 2.4224: Upgrade controls on compressors | $2,498 | $12,500 |
$2,498
21,723
kWh
|
- | - | |
| 06 | 2.1321: Replace fossil fuel equipment with electrical equipment | $78,865 | $433,647 |
$(-1,550.0)
(-13,478)
kWh
|
$8,415
-
MMBtu
|
$72,000 | |
| TOTAL RECOMMENDED | $90,513 | $451,957 |
$10,098
87,810
kWh
|
$8,415
-
MMBtu
|
$72,000 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | LPG Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs