ITAC Assessment: LS2511
ITAC logo
ITAC Assessment: LS2511
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Seafood Processing
NAICS 311710: Seafood Product Preparation and Packaging
SIC 2091: Canned and Cured Fish and Seafoods
Sales Range $50
M
to 100
M
# of Employees 80
Plant Area 50,000
ft2
Annual Production 15,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $314,204 3,923,000
kWh
Electricity Demand $44,471 9,994
kW-mo/yr
TOTAL YEARLY COSTS $358,675
RECOMMENDED SAVINGS* $84,664 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.7135: Install occupancy sensors $2,926 $250 $2,926
36,582
kWh
- -
02 2.7211: Clean and maintain refrigerant condensers and towers $1,062 $288 $1,062
13,281
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $4,592 $2,900 $4,267
53,348
kWh
$325
-
kW-mo/yr
-
04 4.652: Replace existing equipment with more suitable substitutes $31,553 $60,000 $10,428
130,349
kWh
- $21,125
05 2.4226: Use / purchase optimum sized compressor $1,354 $2,700 $1,354
16,921
kWh
- -
06 2.4226: Use / purchase optimum sized compressor $4,879 $15,000 $4,879
60,985
kWh
- -
07 2.2511: Insulate bare equipment $2,489 $10,000 $2,489
31,115
kWh
- -
08 2.9114: Use solar heat to make electricty $35,809 $231,660 $35,809
447,614
kWh
- -
TOTAL RECOMMENDED $84,664 $322,798 $63,214
790,195
kWh
$325
-
kW-mo/yr
$21,125
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs