| Assessment Year | 2025 |
|---|---|
| Principal Product | CNC Machined Parts |
| NAICS | 332710: Machine Shops |
| SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 44 |
| Plant Area |
53,544
ft2
|
| Annual Production | 1,800,000
units
|
| Production Hrs. Annual | 4,862
hrs
|
| Location (State) | Louisiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $66,137 | 649,680 |
kWh
|
$0.10 |
| Electricity Demand | $12,326 | 2,726 |
kW-mo/yr
|
$4.52 |
| Other Gas | $1,045 | 38 |
MMBtu
|
$27.50 |
| TOTAL YEARLY COSTS | $79,508 | |||
| RECOMMENDED SAVINGS* | $69,026 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $771 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $771 | $675 |
$694
6,806
kWh
|
$77
-
kW-mo/yr
|
- | - | |
| 02 | 2.8117: Install sub-metering equipment | $3,313 | $3,000 |
$3,313
32,484
kWh
|
- | - | - | |
| 03 | 4.322: Eliminate old stock and modify inventory control | $9,000 | $25,000 | - | - | - | $9,000 | |
| 04 | 2.7232: Replace existing hvac unit with high efficiency model | $1,488 | $5,190 |
$1,488
14,586
kWh
|
- | - | - | |
| 05 | 2.9114: Use solar heat to make electricty | $39,572 | $160,992 |
$39,572
387,960
kWh
|
- | - | - | |
| 06 | 2.4133: Use most efficient type of electric motors | $2,510 | $10,600 |
$2,510
24,612
kWh
|
- | - | - | |
| 07 | 2.4226: Use / purchase optimum sized compressor | $3,709 | $16,949 |
$3,709
36,365
kWh
|
- | - | - | |
| 08 | 2.1321: Replace fossil fuel equipment with electrical equipment | $8,663 | $48,183 |
$(-382.0)
(-3,744)
kWh
|
- |
$1,045
-
MMBtu
|
$8,000 | |
| TOTAL RECOMMENDED | $69,026 | $270,589 |
$50,904
499,069
kWh
|
$77
-
kW-mo/yr
|
$1,045
-
MMBtu
|
$17,000 | ||
| TOTAL IMPLEMENTED | $771 | $675 |
$694
6,806
kWh
|
$77
-
kW-mo/yr
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs