Assessment Year | 2023 |
---|---|
Principal Product | Brick And Structural Clay Tile |
NAICS | 327331: Concrete Block and Brick Manufacturing |
SIC | 3251: Brick and Structural Clay Tile |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
206,000
ft2
|
Annual Production | 27,000,000
pieces
|
Production Hrs. Annual | 3,276
hrs
|
Location (State) | Louisiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $425,745 | 3,926,900 |
kWh
|
$0.11 |
Electricity Demand | $15,359 | 3,924 |
kW-mo/yr
|
$3.91 |
Natural Gas | $765,807 | 109,643 |
MMBtu
|
$6.98 |
TOTAL YEARLY COSTS | $1,206,911 | |||
RECOMMENDED SAVINGS* | $16,415 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $563 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7134: Use photocell controls | $194 | $25 |
$194
1,797
kWh
|
- | - | |
02 | 2.7261: Install timers and/or thermostats | $136 | $50 |
$136
1,256
kWh
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $563 | $525 |
$496
4,586
kWh
|
$67
-
kW-mo/yr
|
- | |
04 | 2.7135: Install occupancy sensors | $162 | $250 |
$162
1,498
kWh
|
- | - | |
05 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $15,360 | $50,040 | - | - |
$15,360
-
MMBtu
|
|
TOTAL RECOMMENDED | $16,415 | $50,890 |
$988
9,137
kWh
|
$67
-
kW-mo/yr
|
$15,360
-
MMBtu
|
||
TOTAL IMPLEMENTED | $563 | $525 |
$496
4,586
kWh
|
$67
-
kW-mo/yr
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs