ITAC Assessment: LS2312
ITAC logo
ITAC Assessment: LS2312
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Brick And Structural Clay Tile
NAICS 327331: Concrete Block and Brick Manufacturing
SIC 3251: Brick and Structural Clay Tile
Sales Range $10
M
to 50
M
# of Employees 50
Plant Area 206,000
ft2
Annual Production 27,000,000
pieces
Production Hrs. Annual 3,276
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $425,745 3,926,900
kWh
Electricity Demand $15,359 3,924
kW-mo/yr
Natural Gas $765,807 109,643
MMBtu
TOTAL YEARLY COSTS $1,206,911
RECOMMENDED SAVINGS* $16,415 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $563

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7134: Use photocell controls $194 $25 $194
1,797
kWh
- -
02 2.7261: Install timers and/or thermostats $136 $50 $136
1,256
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $563 $525 $496
4,586
kWh
$67
-
kW-mo/yr
-
04 2.7135: Install occupancy sensors $162 $250 $162
1,498
kWh
- -
05 2.1121: Use insulation in furnaces to facilitate heating / cooling $15,360 $50,040 - - $15,360
-
MMBtu
TOTAL RECOMMENDED $16,415 $50,890 $988
9,137
kWh
$67
-
kW-mo/yr
$15,360
-
MMBtu
TOTAL IMPLEMENTED $563 $525 $496
4,586
kWh
$67
-
kW-mo/yr
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs