ITAC Assessment: LS2306
ITAC logo
ITAC Assessment: LS2306
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Lumber
NAICS 321113: Sawmills
SIC 2421: Sawmills and Planing Mills, General
Sales Range $10
M
to 50
M
# of Employees 30
Plant Area 392,040
ft2
Annual Production 2,600
thousand feet
Production Hrs. Annual 2,340
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $106,979 743,981
kWh
TOTAL YEARLY COSTS $106,979
RECOMMENDED SAVINGS* $38,398 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $38,398

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7261: Install timers and/or thermostats $2,207 $250 $2,207
15,324
kWh
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,709 $225 $1,709
11,866
kWh
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $24,953 $19,950 $24,953
173,282
kWh
04 2.7211: Clean and maintain refrigerant condensers and towers $1,449 $1,273 $1,449
10,063
kWh
05 2.7142: Utilize higher efficiency lamps and/or ballasts $7,379 $8,210 $7,379
51,246
kWh
06 2.7232: Replace existing hvac unit with high efficiency model $701 $5,608 $701
4,867
kWh
TOTAL RECOMMENDED $38,398 $35,516 $38,398
266,648
kWh
TOTAL IMPLEMENTED $38,398 $35,516 $38,398
266,648
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs