ITAC Assessment: LS2207
ITAC logo
ITAC Assessment: LS2207
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Polyvinyl Chloride
NAICS 325211: Plastics Material and Resin Manufacturing
SIC 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers
Sales Range less than $500
k
# of Employees 58
Plant Area 4,053,035
ft2
Annual Production 1,950,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $3,120,600 156,030,000
kWh
TOTAL YEARLY COSTS $3,120,600
RECOMMENDED SAVINGS* $167,492 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $29,958

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7261: Install timers and/or thermostats $1,349 $350 $1,349
67,433
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $12,876 $30,073 $12,876
643,822
kWh
03 2.7232: Replace existing hvac unit with high efficiency model $3,432 $32,496 $3,432
171,601
kWh
04 2.4322: Use or replace with energy efficient substitutes $13,650 $158,575 $13,650
682,500
kWh
05 2.2622: Replace existing chiller with high efficiency model $136,185 $2,775,000 $136,185
6,809,253
kWh
TOTAL RECOMMENDED $167,492 $2,996,494 $167,492
8,374,609
kWh
TOTAL IMPLEMENTED $29,958 $221,144 $29,958
1,497,923
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs