| Assessment Year | 2002 |
|---|---|
| Principal Product | Electrically Insulating Varnishes and Resins |
| NAICS |
n/a
|
| SIC | 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products |
| Sales Range | $10 M to 50M |
| # of Employees | 38 |
| Plant Area |
30,250
ft2
|
| Annual Production | 11,000,000
lb
|
| Production Hrs. Annual | 2,210
hrs
|
| Location (State) | New Jersey |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $57,718 | 709,357 |
kWh
|
$0.081 |
| Electricity Demand | $21,843 | 2,486 |
kW-mo/yr
|
$8.79 |
| Natural Gas | $35,769 | 13,682 |
MMBtu
|
$2.61 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $7,310 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,084 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $599 | $728 |
$461
5,659
kWh
|
$138
-
kW-mo/yr
|
- | |
| 02 | 2.6218: Turn off equipment when not in use | $675 | $130 | - | - |
$675
-
MMBtu
|
|
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $901 | - |
$626
7,693
kWh
|
$275
-
kW-mo/yr
|
- | |
| 04 | 2.4314: Use synthetic lubricant | $448 | $400 |
$282
3,470
kWh
|
$166
-
kW-mo/yr
|
- | |
| 05 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $3,278 | $2,500 | - |
$3,278
-
kW-mo/yr
|
- | |
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,409 | - |
$888
10,917
kWh
|
$521
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $7,310 | $3,758 |
$2,257
27,739
kWh
|
$4,378
-
kW-mo/yr
|
$675
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $2,084 | $130 |
$888
10,917
kWh
|
$521
-
kW-mo/yr
|
$675
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs