ITAC Assessment: LS1903
ITAC logo
ITAC Assessment: LS1903
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Ground Coffee
NAICS 311920: Coffee and Tea Manufacturing
SIC 2095: Roasted Coffee
Sales Range $10
M
to 50
M
# of Employees 10
Plant Area 20,000
ft2
Annual Production 1,500,000
lb
Production Hrs. Annual 2,210
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $12,615 117,760
kWh
Electricity Demand $3,864 636
kW-mo/yr
Natural Gas $15,522 2,062
MMBtu
LPG $32,000 6,400
MMBtu
Fuel Oil #2 $30,000 6,000
MMBtu
Other Energy $6,000 1,200
MMBtu
Waste Disposal Costs
Water Usage $4,068 24
Tgal
TOTAL YEARLY COSTS $104,069
RECOMMENDED SAVINGS* $4,023 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,019

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.6231: Utilize controls to operate equipment only when needed $1,079 $150 $1,079
10,083
kWh
- -
02 2.4231: Reduce the pressure of compressed air to the minimum required $135 - $135
1,260
kWh
- -
03 3.7312: Implement a regular maintenance program to reduce emissions from leaky valves and pipe fittings $839 - $839
7,833
kWh
- -
04 2.2136: Install / repair insulation on steam lines $480 $240 - - $480
-
MMBtu
05 2.6218: Turn off equipment when not in use $45 - $45
423
kWh
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,445 $2,189 $1,080
10,091
kWh
$365
-
kW-mo/yr
-
TOTAL RECOMMENDED $4,023 $2,579 $3,178
29,690
kWh
$365
-
kW-mo/yr
$480
-
MMBtu
TOTAL IMPLEMENTED $1,019 - $1,019
9,516
kWh
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs