Assessment Year | 2018 |
---|---|
Principal Product | Beer |
NAICS | 312120: Breweries |
SIC | 2082: Malt Beverages |
Sales Range | $1 M to 5M |
# of Employees | 30 |
Plant Area |
20,000
ft2
|
Annual Production | 310
Tgal
|
Production Hrs. Annual | 3,640
hrs
|
Location (State) | Louisiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $36,845 | 375,384 |
kWh
|
$0.098 | |
Electricity Demand | $6,366 | 950 |
kW-mo/yr
|
$6.70 | |
Electricity Fees | $16,000 | - |
|
- | |
Natural Gas | $16,742 | 2,069 |
MMBtu
|
$8.09 | |
LPG | $10,000 | 2,000 |
MMBtu
|
$5.00 | |
Other Gas | $10,000 | 2,000 |
MMBtu
|
$5.00 | |
Other Energy | $5,000 | 1,000 |
MMBtu
|
$5.00 | |
Waste Disposal Costs | |||||
Water Usage | $16,060 | 1,313 |
Tgal
|
$12.23 | |
TOTAL YEARLY COSTS | $117,013 | ||||
RECOMMENDED SAVINGS* | $3,675 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $2,630 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $358 | $25 |
$358
3,651
kWh
|
- | - | |
02 | 2.2136: Install / repair insulation on steam lines | $880 | $340 | - | - |
$880
-
MMBtu
|
|
03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $650 | $650 |
$650
6,784
kWh
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $986 | $1,088 |
$825
8,416
kWh
|
$161
-
kW-mo/yr
|
- | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $37 | $55 |
$37
374
kWh
|
- | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $764 | $1,800 |
$764
7,787
kWh
|
- | - | |
TOTAL RECOMMENDED | $3,675 | $3,958 |
$2,634
27,012
kWh
|
$161
-
kW-mo/yr
|
$880
-
MMBtu
|
||
TOTAL IMPLEMENTED | $2,630 | $3,228 |
$1,589
16,203
kWh
|
$161
-
kW-mo/yr
|
$880
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs