ITAC Assessment: LS1809
ITAC logo
ITAC Assessment: LS1809
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Processed meats
NAICS 311612: Meat Processed from Carcasses
SIC 2013: Sausages and Other Prepared Meat Products
Sales Range $1
M
to 5
M
# of Employees 22
Plant Area 33,000
ft2
Annual Production 13,730,000
units
Production Hrs. Annual 2,080
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $72,768 850,080
kWh
Electricity Demand $17,616 1,992
kW-mo/yr
Natural Gas $9,937 1,202
MMBtu
Waste Disposal Costs
Water Usage $9,167 536
Tgal
TOTAL YEARLY COSTS $109,488
RECOMMENDED SAVINGS* $13,069 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $1,090 $100 - $1,090
-
kW-mo/yr
-
02 2.7447: Install vinyl strip / high speed / air curtain doors $134 $45 $134
1,560
kWh
- -
03 2.7135: Install occupancy sensors $401 $300 $401
4,659
kWh
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $4,902 $4,019 $3,097
36,017
kWh
$1,805
-
kW-mo/yr
-
05 2.2511: Insulate bare equipment $364 $440 - - $364
-
MMBtu
06 2.4231: Reduce the pressure of compressed air to the minimum required $33 $50 $33
391
kWh
- -
07 2.1243: Use heat from boiler blowdown to preheat boiler feed water $6,145 $11,000 - - $6,145
-
MMBtu
TOTAL RECOMMENDED $13,069 $15,954 $3,665
42,627
kWh
$2,895
-
kW-mo/yr
$6,509
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs