ITAC Assessment: LS1807
ITAC logo
ITAC Assessment: LS1807
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Refined Natural Gas Liquids, Ethane, Propane, Butane, Amine
NAICS 325998: All Other Miscellaneous Chemical Product and Preparation Manufacturing
SIC 2869: Industrial Organic Chemicals, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 11
Plant Area 1,676,691
ft2
Annual Production 1,740,000
units
Production Hrs. Annual 8,760
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $765,914 15,327,000
kWh
Electricity Demand $182,400 30,000
kW-mo/yr
Electricity Fees $3,305 -
TOTAL YEARLY COSTS $951,619
RECOMMENDED SAVINGS* $83,071 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings
01 2.8123: Pay utility bills on time $3,305 $50 - $3,305
02 2.7447: Install vinyl strip / high speed / air curtain doors $70 $60 $70
1,408
kWh
-
03 3.7312: Implement a regular maintenance program to reduce emissions from leaky valves and pipe fittings $853 $840 $853
17,076
kWh
-
04 2.7447: Install vinyl strip / high speed / air curtain doors $109 $170 $109
2,176
kWh
-
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $78,734 $244,800 $78,734
1,575,568
kWh
-
TOTAL RECOMMENDED $83,071 $245,920 $79,766
1,596,228
kWh
$3,305
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs