ITAC Assessment: LS1803
ITAC logo
ITAC Assessment: LS1803
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Beer
NAICS 312120: Breweries
SIC 2082: Malt Beverages
Sales Range $1
M
to 5
M
# of Employees 40
Plant Area 20,000
ft2
Annual Production 310,000
units
Production Hrs. Annual 3,640
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $37,407 393,396
kWh
Electricity Demand $5,589 945
kW-mo/yr
Natural Gas $19,274 2,513
MMBtu
TOTAL YEARLY COSTS $62,270
RECOMMENDED SAVINGS* $2,604 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,121

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.7447: Install vinyl strip / high speed / air curtain doors $544 $220 $544
5,756
kWh
- - -
02 2.4231: Reduce the pressure of compressed air to the minimum required $437 $300 $437
4,600
kWh
- - -
03 2.2511: Insulate bare equipment $179 $156 - - $179
-
MMBtu
-
04 3.1161: Eliminate/reduce an operation $600 $620 - - - $600
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $39 $95 $39
412
kWh
- - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $577 $2,755 $478
5,067
kWh
$99
-
kW-mo/yr
- -
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $228 $1,800 $228
2,401
kWh
- - -
TOTAL RECOMMENDED $2,604 $5,946 $1,726
18,236
kWh
$99
-
kW-mo/yr
$179
-
MMBtu
$600
TOTAL IMPLEMENTED $1,121 $2,975 $1,022
10,823
kWh
$99
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs