Assessment Year | 2022 |
---|---|
Principal Product | Offices |
NAICS | 541330: Engineering Services |
SIC | 8748: Business Consulting Services, Not Elsewhere Classified |
Sales Range | less than $500 k |
# of Employees | 10 |
Plant Area |
216,720
ft2
|
Annual Production | 1
units
|
Production Hrs. Annual | 2,600
hrs
|
Location (State) | Louisiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $768,137 | 7,433,850 |
kWh
|
$0.10 |
Electricity Demand | $88,992 | 22,250 |
kW-mo/yr
|
$4.00 |
Natural Gas | $26,472 | 2,625 |
MMBtu
|
$10.08 |
TOTAL YEARLY COSTS | $883,601 | |||
RECOMMENDED SAVINGS* | $97,154 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $91,981 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $59,902 | $3,750 |
$59,902
581,569
kWh
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $32,079 | $33,425 |
$27,463
226,630
kWh
|
$4,616
-
kW-mo/yr
|
|
03 | 2.7135: Install occupancy sensors | $3,599 | $4,375 |
$3,599
34,944
kWh
|
- | |
04 | 2.7243: Improve air circulation with destratification fans / other methods | $702 | $1,050 |
$702
6,811
kWh
|
- | |
05 | 2.7232: Replace existing hvac unit with high efficiency model | $872 | $4,215 |
$872
8,465
kWh
|
- | |
TOTAL RECOMMENDED | $97,154 | $46,815 |
$92,538
858,419
kWh
|
$4,616
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $91,981 | $37,175 |
$87,365
808,199
kWh
|
$4,616
-
kW-mo/yr
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs