ITAC Assessment: LS0522
ITAC logo
ITAC Assessment: LS0522
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Aircraft hangar rental and terminal
NAICS 488119: Other Airport Operations
SIC 4581: Airports, Flying Fields, and Airport Terminal Services
Sales Range less than $500
k
# of Employees 3
Plant Area 100,000
ft2
Annual Production 1
units
Production Hrs. Annual 3,650
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $14,532 118,604
kWh
Electricity Demand $1,388 455
kW-mo/yr
TOTAL YEARLY COSTS $15,920
RECOMMENDED SAVINGS* $5,555 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,430

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7261: Install timers and/or thermostats $1,249 $38 $1,249
10,192
kWh
-
02 2.7135: Install occupancy sensors $57 $25 $57
467
kWh
-
03 2.7447: Install vinyl strip / high speed / air curtain doors $125 $80 $125
1,017
kWh
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $4,124 $3,917 $3,708
30,262
kWh
$416
-
kW-mo/yr
TOTAL RECOMMENDED $5,555 $4,060 $5,139
41,938
kWh
$416
-
kW-mo/yr
TOTAL IMPLEMENTED $5,430 $3,980 $5,014
40,921
kWh
$416
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs