ITAC Assessment: LS0004
ITAC logo
ITAC Assessment: LS0004
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Ready Mix Concrete
NAICS 327320: Ready-Mix Concrete Manufacturing
SIC 3273: Ready-Mixed Concrete
Sales Range $10
M
to 50
M
# of Employees 38
Plant Area 4,000
ft2
Annual Production 10,000
units
Production Hrs. Annual 2,600
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $10,432 69,194
kWh
Electricity Demand $206 36
kW-mo/yr
Fuel Oil #1 $275,000 19,971
MMBtu
Waste Disposal Costs
Water Usage $23,590 3,783
Tgal
Water Disposal $283 48
Tgal
TOTAL YEARLY COSTS $309,511
RECOMMENDED SAVINGS* $54,260 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Fuel Oil #1 Savings Personnel Changes Savings Administrative Changes Savings Water Consumption Savings
01 4.111: Add equipment/ operators to reduce production bottleneck $43,789 - - $659
-
MMBtu
$17,252 $25,878 -
02 4.122: Develop standard procedures to improve internal yields $6,311 - - $86
-
MMBtu
$2,850 $3,375 -
03 3.4151: Minimize water usage $2,256 - - - - - $2,256
-
Tgal
04 2.7111: Reduce illumination to minimum necessary levels $627 - $627
4,160
kWh
- - - -
05 2.7134: Use photocell controls $188 - $188
1,248
kWh
- - - -
06 2.7124: Make a practice of turning off lights when not needed $110 - $110
728
kWh
- - - -
07 2.4231: Reduce the pressure of compressed air to the minimum required $444 - $444
2,943
kWh
- - - -
08 2.4111: Utilize energy-efficient belts and other improved mechanisms $203 - $203
1,345
kWh
- - - -
09 2.7224: Reduce space conditioning during non-working hours $68 - $68
451
kWh
- - - -
10 2.7447: Install vinyl strip / high speed / air curtain doors $23 - $23
152
kWh
- - - -
11 2.8123: Pay utility bills on time $241 - - - - $241 -
TOTAL RECOMMENDED $54,260 - $1,663
11,027
kWh
$745
-
MMBtu
$20,102 $29,494 $2,256
-
Tgal
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Fuel Oil #1 Savings Personnel Changes Savings Administrative Changes Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs