| Assessment Year | 2017 |
|---|---|
| Principal Product | Ready Mix Concrete |
| NAICS | 327320: Ready-Mix Concrete Manufacturing |
| SIC | 3273: Ready-Mixed Concrete |
| Sales Range | $10 M to 50M |
| # of Employees | 38 |
| Plant Area |
4,000
ft2
|
| Annual Production | 10,000
units
|
| Production Hrs. Annual | 2,600
hrs
|
| Location (State) | Louisiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $10,432 | 69,194 |
kWh
|
$0.15 | |
| Electricity Demand | $206 | 36 |
kW-mo/yr
|
$5.77 | |
| Fuel Oil #1 | $275,000 | 19,971 |
MMBtu
|
$13.77 | |
| Waste Disposal Costs | |||||
| Water Usage | $23,590 | 3,783 |
Tgal
|
$6.24 | |
| Water Disposal | $283 | 48 |
Tgal
|
$5.91 | |
| TOTAL YEARLY COSTS | $309,511 | ||||
| RECOMMENDED SAVINGS* | $54,260 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #1 Savings | Personnel Changes Savings | Administrative Changes Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.111: Add equipment/ operators to reduce production bottleneck | $43,789 | - | - |
$659
-
MMBtu
|
$17,252 | $25,878 | - | |
| 02 | 4.122: Develop standard procedures to improve internal yields | $6,311 | - | - |
$86
-
MMBtu
|
$2,850 | $3,375 | - | |
| 03 | 3.4151: Minimize water usage | $2,256 | - | - | - | - | - |
$2,256
-
Tgal
|
|
| 04 | 2.7111: Reduce illumination to minimum necessary levels | $627 | - |
$627
4,160
kWh
|
- | - | - | - | |
| 05 | 2.7134: Use photocell controls | $188 | - |
$188
1,248
kWh
|
- | - | - | - | |
| 06 | 2.7124: Make a practice of turning off lights when not needed | $110 | - |
$110
728
kWh
|
- | - | - | - | |
| 07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $444 | - |
$444
2,943
kWh
|
- | - | - | - | |
| 08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $203 | - |
$203
1,345
kWh
|
- | - | - | - | |
| 09 | 2.7224: Reduce space conditioning during non-working hours | $68 | - |
$68
451
kWh
|
- | - | - | - | |
| 10 | 2.7447: Install vinyl strip / high speed / air curtain doors | $23 | - |
$23
152
kWh
|
- | - | - | - | |
| 11 | 2.8123: Pay utility bills on time | $241 | - | - | - | - | $241 | - | |
| TOTAL RECOMMENDED | $54,260 | - |
$1,663
11,027
kWh
|
$745
-
MMBtu
|
$20,102 | $29,494 |
$2,256
-
Tgal
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #1 Savings | Personnel Changes Savings | Administrative Changes Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs