Assessment Year | 2005 |
---|---|
Principal Product | PVC cement |
NAICS | 325520: Adhesive Manufacturing |
SIC | 2891: Adhesives and Sealants |
Sales Range | $50 M to 100M |
# of Employees | 200 |
Plant Area |
100,000
ft2
|
Annual Production | 50,000,000
lb
|
Production Hrs. Annual | 4,576
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $210,116 | 2,002,199 |
kWh
|
$0.10 |
Electricity Demand | $66,319 | 629 |
kW-mo/yr
|
$105.44 |
Electricity Fees | $11,065 | - |
|
- |
Natural Gas | $1,070 | 88 |
MMBtu
|
$12.16 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $38,468 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,607 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,607 | $475 |
$1,316
12,768
kWh
|
$291
-
kW-mo/yr
|
- | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,940 | - |
$1,591
15,440
kWh
|
$349
-
kW-mo/yr
|
- | |
03 | 2.4221: Install compressor air intakes in coolest locations | $903 | $200 |
$740
7,178
kWh
|
$163
-
kW-mo/yr
|
- | |
04 | 2.7124: Make a practice of turning off lights when not needed | $1,570 | $150 |
$1,441
13,985
kWh
|
$129
-
kW-mo/yr
|
- | |
05 | 4.426: Modify workload | $32,448 | $300 | - | - | $32,448 | |
TOTAL RECOMMENDED | $38,468 | $1,125 |
$5,088
49,371
kWh
|
$932
-
kW-mo/yr
|
$32,448 | ||
TOTAL IMPLEMENTED | $1,607 | $475 |
$1,316
12,768
kWh
|
$291
-
kW-mo/yr
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs