Assessment Year | 2004 |
---|---|
Principal Product | metal forming |
NAICS | 332439: Other Metal Container Manufacturing |
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 60 |
Plant Area |
79,000
ft2
|
Annual Production | 26,400
pieces
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $70,170 | 679,200 |
kWh
|
$0.10 |
Electricity Demand | $19,020 | 2,244 |
kW-mo/yr
|
$8.48 |
Electricity Fees | $(-2,636.0) | - |
|
- |
Natural Gas | $67,242 | 8,758 |
MMBtu
|
$7.68 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $13,400 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,975 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,003 | $300 |
$1,682
15,457
kWh
|
$321
-
kW-mo/yr
|
- | |
02 | 2.4221: Install compressor air intakes in coolest locations | $991 | $250 |
$832
7,770
kWh
|
$159
-
kW-mo/yr
|
- | |
03 | 3.3131: Use evaporation to concentrate material | $7,975 | $3,000 |
$(-4,025.0)
(-37,575)
kWh
|
- |
$12,000
-
Tgal
|
|
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,349 | - |
$1,972
18,414
kWh
|
$377
-
kW-mo/yr
|
- | |
05 | 2.4133: Use most efficient type of electric motors | $82 | $126 |
$69
641
kWh
|
$13
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $13,400 | $3,676 |
$530
4,707
kWh
|
$870
-
kW-mo/yr
|
$12,000
-
Tgal
|
||
TOTAL IMPLEMENTED | $7,975 | $3,000 |
$(-4,025.0)
(-37,575)
kWh
|
- |
$12,000
-
Tgal
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs