| Assessment Year | 2004 |
|---|---|
| Principal Product | stainless plumbing |
| NAICS | 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing |
| SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 500 |
| Plant Area |
136,700
ft2
|
| Annual Production | 500,000
lb
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $195,557 | 2,237,735 |
kWh
|
$0.087 |
| Electricity Demand | $85,976 | 7,668 |
kW-mo/yr
|
$11.21 |
| Electricity Fees | $3,850 | - |
|
- |
| Natural Gas | $9,472 | 1,190 |
MMBtu
|
$7.96 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $63,698 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $37,600 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,069 | $17,418 |
$4,370
50,160
kWh
|
$1,699
-
kW-mo/yr
|
- | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,466 | $760 |
$7,538
86,520
kWh
|
$2,928
-
kW-mo/yr
|
- | - | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,413 | - |
$1,017
11,670
kWh
|
$396
-
kW-mo/yr
|
- | - | |
| 04 | 2.3132: Recharge batteries on during off-peak demand periods | $1,685 | $450 |
$709
-
kWh
|
$976
-
kW-mo/yr
|
- | - | |
| 05 | 2.4133: Use most efficient type of electric motors | $244 | $377 |
$139
1,597
kWh
|
$105
-
kW-mo/yr
|
- | - | |
| 06 | 2.4226: Use / purchase optimum sized compressor | $1,321 | $1,000 |
$951
10,912
kWh
|
$370
-
kW-mo/yr
|
- | - | |
| 07 | 4.426: Modify workload | $23,000 | $9,700 | - | - | $23,000 | - | |
| 08 | 4.122: Develop standard procedures to improve internal yields | $19,500 | $3,680 | - | - | - | $19,500 | |
| TOTAL RECOMMENDED | $63,698 | $33,385 |
$14,724
160,859
kWh
|
$6,474
-
kW-mo/yr
|
$23,000 | $19,500 | ||
| TOTAL IMPLEMENTED | $37,600 | $23,235 |
$12,998
149,189
kWh
|
$5,102
-
kW-mo/yr
|
- | $19,500 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs