Assessment Year | 2004 |
---|---|
Principal Product | Margarine |
NAICS | 311225: Fats and Oils Refining and Blending |
SIC | 2079: Shortening, Table Oils, Margarine, and Other Edible Fats and Oils, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 108 |
Plant Area |
180,000
ft2
|
Annual Production | 130,000,000
lb
|
Production Hrs. Annual | 5,000
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $101,282 | 5,062,920 |
kWh
|
$0.020 |
Electricity Demand | $151,639 | 12,072 |
kW-mo/yr
|
$12.56 |
Electricity Fees | $249,201 | - |
|
- |
Natural Gas | $167,999 | 23,899 |
MMBtu
|
$7.03 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $145,392 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,698 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,653 | - |
$1,133
20,335
kWh
|
$520
-
kW-mo/yr
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,307 | $100 |
$895
16,080
kWh
|
$412
-
kW-mo/yr
|
- | - | - | |
03 | 2.2135: Repair and eliminate steam leaks | $3,173 | $396 | - | - |
$3,173
-
MMBtu
|
- | - | |
04 | 3.5217: Reuse / recycle/ sell paper products | $438 | - | - | - | - | - | $438 | |
05 | 2.2121: Increase amount of condensate returned | $620 | $800 | - | - |
$620
-
MMBtu
|
- | - | |
06 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,058 | $1,800 |
$365
6,552
kWh
|
$921
-
kW-mo/yr
|
$(-228.0)
-
MMBtu
|
- | - | |
07 | 2.2123: Insulate feedwater tank | $329 | $507 | - | - |
$329
-
MMBtu
|
- | - | |
08 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,604 | $250 |
$1,220
21,900
kWh
|
$384
-
kW-mo/yr
|
- | - | - | |
09 | 2.4133: Use most efficient type of electric motors | $2,089 | $983 |
$1,511
27,132
kWh
|
$578
-
kW-mo/yr
|
- | - | - | |
10 | 4.514: Re-arrange equipment layout to reduce handling costs | $121,324 | $125,104 |
$1,324
23,760
kWh
|
- | - | $120,000 | - | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,231 | $20,284 |
$6,326
113,556
kWh
|
$2,905
-
kW-mo/yr
|
- | - | - | |
12 | 2.7111: Reduce illumination to minimum necessary levels | $614 | - |
$421
7,560
kWh
|
$193
-
kW-mo/yr
|
- | - | - | |
13 | 2.7132: Install timers on light switches in little used areas | $1,952 | $450 |
$1,337
24,012
kWh
|
$615
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $145,392 | $150,674 |
$14,532
260,887
kWh
|
$6,528
-
kW-mo/yr
|
$3,894
-
MMBtu
|
$120,000 | $438 | ||
TOTAL IMPLEMENTED | $6,698 | $746 |
$2,536
45,540
kWh
|
$989
-
kW-mo/yr
|
$3,173
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs