ITAC Assessment: LM0084
ITAC logo
ITAC Assessment: LM0084
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Margarine
NAICS 311225: Fats and Oils Refining and Blending
SIC 2079: Shortening, Table Oils, Margarine, and Other Edible Fats and Oils, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 108
Plant Area 180,000
ft2
Annual Production 130,000,000
lb
Production Hrs. Annual 5,000
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $101,282 5,062,920
kWh
Electricity Demand $151,639 12,072
kW-mo/yr
Electricity Fees $249,201 -
Natural Gas $167,999 23,899
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $145,392 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,698

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $1,653 - $1,133
20,335
kWh
$520
-
kW-mo/yr
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,307 $100 $895
16,080
kWh
$412
-
kW-mo/yr
- - -
03 2.2135: Repair and eliminate steam leaks $3,173 $396 - - $3,173
-
MMBtu
- -
04 3.5217: Reuse / recycle/ sell paper products $438 - - - - - $438
05 2.2121: Increase amount of condensate returned $620 $800 - - $620
-
MMBtu
- -
06 2.1311: Replace electrically-operated equipment with fossil fuel equipment $1,058 $1,800 $365
6,552
kWh
$921
-
kW-mo/yr
$(-228.0)
-
MMBtu
- -
07 2.2123: Insulate feedwater tank $329 $507 - - $329
-
MMBtu
- -
08 2.7447: Install vinyl strip / high speed / air curtain doors $1,604 $250 $1,220
21,900
kWh
$384
-
kW-mo/yr
- - -
09 2.4133: Use most efficient type of electric motors $2,089 $983 $1,511
27,132
kWh
$578
-
kW-mo/yr
- - -
10 4.514: Re-arrange equipment layout to reduce handling costs $121,324 $125,104 $1,324
23,760
kWh
- - $120,000 -
11 2.7142: Utilize higher efficiency lamps and/or ballasts $9,231 $20,284 $6,326
113,556
kWh
$2,905
-
kW-mo/yr
- - -
12 2.7111: Reduce illumination to minimum necessary levels $614 - $421
7,560
kWh
$193
-
kW-mo/yr
- - -
13 2.7132: Install timers on light switches in little used areas $1,952 $450 $1,337
24,012
kWh
$615
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $145,392 $150,674 $14,532
260,887
kWh
$6,528
-
kW-mo/yr
$3,894
-
MMBtu
$120,000 $438
TOTAL IMPLEMENTED $6,698 $746 $2,536
45,540
kWh
$989
-
kW-mo/yr
$3,173
-
MMBtu
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs