| Assessment Year | 2008 |
|---|---|
| Principal Product | Equipment used for biomedical research |
| NAICS | 332618: Other Fabricated Wire Product Manufacturing |
| SIC | 3496: Miscellaneous Fabricated Wire Products |
| Sales Range | $100 M to 500M |
| # of Employees | 365 |
| Plant Area |
196,000
ft2
|
| Annual Production | 1
units
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | New Jersey |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $228,931 | 2,289,631 |
kWh
|
$0.100 |
| Electricity Demand | $43,917 | 6,688 |
kW-mo/yr
|
$6.57 |
| Natural Gas | $17,355 | 1,104 |
MMBtu
|
$15.72 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $40,183 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $12,555 | $1,000 |
$10,555
105,548
kWh
|
$2,000
-
kW-mo/yr
|
|
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $11,354 | $15,000 |
$9,545
95,448
kWh
|
$1,809
-
kW-mo/yr
|
|
| 03 | 2.4226: Use / purchase optimum sized compressor | $3,444 | $500 |
$2,566
25,655
kWh
|
$878
-
kW-mo/yr
|
|
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,656 | $130 |
$2,656
26,564
kWh
|
- | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,432 | $200 |
$2,009
20,094
kWh
|
$423
-
kW-mo/yr
|
|
| 06 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,194 | $2,500 | - |
$2,194
-
kW-mo/yr
|
|
| 07 | 2.4221: Install compressor air intakes in coolest locations | $884 | $800 |
$727
7,273
kWh
|
$157
-
kW-mo/yr
|
|
| 08 | 2.9112: Use solar heat to heat water | $354 | $1,260 |
$354
3,543
kWh
|
- | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,555 | $3,555 |
$3,006
30,060
kWh
|
$549
-
kW-mo/yr
|
|
| 10 | 2.7135: Install occupancy sensors | $755 | $60 |
$755
7,550
kWh
|
- | |
| TOTAL RECOMMENDED | $40,183 | $25,005 |
$32,173
321,735
kWh
|
$8,010
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs