ITAC Assessment: LM0083
ITAC logo
ITAC Assessment: LM0083
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Plastic recycling
NAICS 325991: Custom Compounding of Purchased Resins
SIC 3087: Custom Compounding of Purchased Plastics Resins
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 120,000
ft2
Annual Production 26,000,000
lb
Production Hrs. Annual 7,200
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $384,139 3,979,664
kWh
Electricity Demand $151,861 11,856
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $60,092 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $946

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $28,411 $5,040 $19,461
271,273
kWh
$8,950
-
kW-mo/yr
-
02 2.4231: Reduce the pressure of compressed air to the minimum required $836 - $682
7,111
kWh
$154
-
kW-mo/yr
-
03 2.4239: Eliminate or reduce compressed air usage $110 $150 $110
1,275
kWh
- -
04 4.122: Develop standard procedures to improve internal yields $21,186 $3,081 - - $21,186
05 4.422: Utilize outside contracting $4,988 $500 - - $4,988
06 2.4226: Use / purchase optimum sized compressor $4,561 $8,800 $3,724
38,822
kWh
$837
-
kW-mo/yr
-
TOTAL RECOMMENDED $60,092 $17,571 $23,977
318,481
kWh
$9,941
-
kW-mo/yr
$26,174
TOTAL IMPLEMENTED $946 $150 $792
8,386
kWh
$154
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs