Assessment Year | 2015 |
---|---|
Principal Product | road construction equipment |
NAICS | 333120: Construction Machinery Manufacturing |
SIC | 3531: Construction Machinery and Equipment |
Sales Range | $1 M to 5M |
# of Employees | 25 |
Plant Area |
15,000
ft2
|
Annual Production | 40
pieces
|
Production Hrs. Annual | 2,800
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $78,480 | 1,091,126 |
kWh
|
$0.072 |
Electricity Demand | $19,724 | 2,447 |
kW-mo/yr
|
$8.06 |
Natural Gas | $6,006 | 570 |
MMBtu
|
$10.54 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $6,057 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,389 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,668 | $6,475 |
$1,128
15,680
kWh
|
$540
-
kW-mo/yr
|
|
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,931 | $890 |
$1,980
27,532
kWh
|
$951
-
kW-mo/yr
|
|
03 | 2.4239: Eliminate or reduce compressed air usage | $1,082 | $2,600 |
$985
13,689
kWh
|
$97
-
kW-mo/yr
|
|
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $376 | - |
$255
3,539
kWh
|
$121
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $6,057 | $9,965 |
$4,348
60,440
kWh
|
$1,709
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $4,389 | $3,490 |
$3,220
44,760
kWh
|
$1,169
-
kW-mo/yr
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs