ITAC Assessment: LM0071
ITAC logo
ITAC Assessment: LM0071
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Electronic Test Equipment
NAICS 334515: Instrument Manufacturing for Measuring and Testing Electricity and Electrical Signals
SIC 3825: Instruments for Measuring and Testing of Electricity and Electrical Signals
Sales Range $100
M
to 500
M
# of Employees 400
Plant Area 300,000
ft2
Annual Production 300
pieces
Production Hrs. Annual 2,080
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,315,501 12,590,092
kWh
Electricity Demand $289,368 13,848
kW-mo/yr
Electricity Fees $44,128 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $756,144 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $104,694

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $3,818 $1,176 $3,100
30,069
kWh
$718
-
kW-mo/yr
- - -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $80,552 $121,600 $65,680
637,216
kWh
$14,872
-
kW-mo/yr
- - -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $8,163 $945 $6,960
67,531
kWh
$1,203
-
kW-mo/yr
- - -
04 2.7135: Install occupancy sensors $1,330 $1,200 $1,050
3,728
kWh
$280
-
kW-mo/yr
- - -
05 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $7,879 - $5,706
55,518
kWh
$2,173
-
kW-mo/yr
- - -
06 2.6231: Utilize controls to operate equipment only when needed $99,668 $24,000 $107,312
1,195,672
kWh
- $7,956
-
Tgal
$(-15,600.0) -
07 4.421: Modify current incentive program $3,000 $300 - - - - $3,000
08 4.431: Train operators for maximum operating efficiency $214,912 $3,000 - - - $214,912 -
09 4.522: Modify storage space to avoid rental of a warehouse $252,500 $35,000 - - - - $252,500
10 2.7425: Clean or color roof to reduce solar load $84,322 $100,000 $59,704
400,336
kWh
$24,618
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $756,144 $287,221 $249,512
2,390,070
kWh
$43,864
-
kW-mo/yr
$7,956
-
Tgal
$199,312 $255,500
TOTAL IMPLEMENTED $104,694 $102,445 $73,420
527,113
kWh
$28,274
-
kW-mo/yr
- - $3,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs