ITAC Assessment: MS0354
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product PLASTICS
NAICS 326111: Plastics Bag and Pouch Manufacturing
SIC 2673: Plastics, Foil, and Coated Paper Bags
Sales Range $10
M
to 50
M
# of Employees 33
Plant Area 38,000
ft2
Annual Production 6,000
ton
Production Hrs. Annual 8,568
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $320,001 3,296,480
kWh
Electricity Demand $21,018 5,764
kW-mo/yr
Electricity Fees $5,156 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,216 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $10,040 $6,573 $8,822
210,053
kWh
$1,069
-
kW-mo/yr
$149
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,328 $356 $2,295
54,636
kWh
- $33
03 2.7142: Utilize higher efficiency lamps and/or ballasts $524 $1,365 $447
10,644
kWh
$69
-
kW-mo/yr
$8
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $324 $490 $265
6,305
kWh
$55
-
kW-mo/yr
$4
TOTAL RECOMMENDED $13,216 $8,784 $11,829
281,638
kWh
$1,193
-
kW-mo/yr
$194
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs