ITAC Assessment: LM0061
ITAC logo
ITAC Assessment: LM0061
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Steel and Concrete Pipe
NAICS 327332: Concrete Pipe Manufacturing
SIC 3272: Concrete Products, Except Block and Brick
Sales Range $10
M
to 50
M
# of Employees 180
Plant Area 348,480
ft2
Annual Production 140,000
ton
Production Hrs. Annual 4,000
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $314,466 3,788,112
kWh
Electricity Demand $126,392 17,028
kW-mo/yr
Electricity Fees $66,212 -
Natural Gas $160,204 45,451
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $768,030 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $409,626

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Increase in Production Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,107 $430 $2,282
29,692
kWh
$511
-
kW-mo/yr
- $(-686.0) - -
02 2.4226: Use / purchase optimum sized compressor $78,994 $149,000 $66,122
745,680
kWh
$12,872
-
kW-mo/yr
- - - -
03 2.4133: Use most efficient type of electric motors $1,049 $1,281 $812
10,559
kWh
$237
-
kW-mo/yr
- - - -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $320 $288 $246
3,212
kWh
$74
-
kW-mo/yr
- - - -
05 2.7124: Make a practice of turning off lights when not needed $4,642 - $3,592
46,742
kWh
$1,050
-
kW-mo/yr
- - - -
06 2.1233: Analyze flue gas for proper air/fuel ratio $12,290 $1,000 - - $13,290
-
MMBtu
$(-1,000.0) - -
07 2.7229: Air condition only space necessary $530 - - - $530
-
MMBtu
- - -
08 3.1182: Make a new by-product $20,000 $300 - - - - $20,000 -
09 4.454: Modify startup/shutdown times $11,678 $25,000 $17,438
-
kWh
- - $(-5,760.0) - -
10 4.431: Train operators for maximum operating efficiency $42,240 $25,000 - - - $42,240 - -
11 4.431: Train operators for maximum operating efficiency $360,180 $35,000 - - - $360,180 - -
12 4.611: Begin a practice of predictive / preventative maintenance $200,000 $7,500 - - - - - $200,000
13 4.421: Modify current incentive program $34,000 $5,000 - - - - - $34,000
TOTAL RECOMMENDED $768,030 $249,799 $90,492
835,885
kWh
$14,744
-
kW-mo/yr
$13,820
-
MMBtu
$394,974 $20,000 $234,000
TOTAL IMPLEMENTED $409,626 $42,711 $3,094
40,251
kWh
$748
-
kW-mo/yr
$13,290
-
MMBtu
$358,494 - $34,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs