Assessment Year | 2002 |
---|---|
Principal Product | iron pipe fittings |
NAICS |
n/a
|
SIC | 3498: Fabricated Pipe and Pipe Fittings |
Sales Range | $10 M to 50M |
# of Employees | 80 |
Plant Area |
90,440
ft2
|
Annual Production | 5,428,665
lb
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $170,878 | 2,055,357 |
kWh
|
$0.083 |
Electricity Demand | $69,859 | 8,748 |
kW-mo/yr
|
$7.99 |
Electricity Fees | $25,327 | - |
|
- |
Natural Gas | $45,689 | 8,557 |
MMBtu
|
$5.34 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $180,007 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,476 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,685 | $450 |
$2,855
27,000
kWh
|
$610
-
kW-mo/yr
|
- | $(-780.0) | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,048 | $600 |
$1,484
14,040
kWh
|
$564
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,476 | $288 |
$1,240
11,737
kWh
|
$236
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.7124: Make a practice of turning off lights when not needed | $2,360 | $1,440 |
$1,586
15,004
kWh
|
$774
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.2414: Use waste heat from hot flue gases to preheat | $4,888 | $9,000 | - | - |
$4,888
-
MMBtu
|
- | - | - | |
06 | 4.121: Maintain clean conditions before painting | $108,300 | $200 | - | - | - | - | $108,300 | - | |
07 | 4.132: Purchase new equipment to reduce material use / cost | $45,250 | $1,332 | - | - | - | - | - | $45,250 | |
08 | 4.513: Re-arrange equipment layout to reduce labor costs | $13,000 | $3,900 | - | - | - | $13,000 | - | - | |
TOTAL RECOMMENDED | $180,007 | $17,210 |
$7,165
67,781
kWh
|
$2,184
-
kW-mo/yr
|
$4,888
-
MMBtu
|
$12,220 | $108,300 | $45,250 | ||
TOTAL IMPLEMENTED | $1,476 | $288 |
$1,240
11,737
kWh
|
$236
-
kW-mo/yr
|
- | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs