Assessment Year | 2002 |
---|---|
Principal Product | metal stampings |
NAICS |
n/a
|
SIC | 3484: Small Arms |
Sales Range | $1 M to 5M |
# of Employees | 50 |
Plant Area |
38,000
ft2
|
Annual Production | 60,000,000
pieces
|
Production Hrs. Annual | 2,600
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $55,662 | 539,958 |
kWh
|
$0.10 |
Electricity Demand | $32,413 | 3,996 |
kW-mo/yr
|
$8.11 |
Electricity Fees | $5,375 | - |
|
- |
Natural Gas | $4,993 | 515 |
MMBtu
|
$9.70 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $40,037 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $20,000 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,575 | $2,880 |
$1,228
10,264
kWh
|
$347
-
kW-mo/yr
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,338 | $550 |
$3,773
31,542
kWh
|
$1,345
-
kW-mo/yr
|
$(-780.0) | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $211 | $228 |
$161
1,350
kWh
|
$50
-
kW-mo/yr
|
- | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,154 | - |
$883
7,378
kWh
|
$271
-
kW-mo/yr
|
- | - | |
05 | 4.513: Re-arrange equipment layout to reduce labor costs | $2,496 | $900 | - | - | $2,496 | - | |
06 | 4.611: Begin a practice of predictive / preventative maintenance | $20,000 | $600 | - | - | $20,000 | - | |
07 | 4.454: Modify startup/shutdown times | $10,263 | $300 | - |
$8,003
-
kW-mo/yr
|
$(-4,500.0) | $6,760 | |
TOTAL RECOMMENDED | $40,037 | $5,458 |
$6,045
50,534
kWh
|
$10,016
-
kW-mo/yr
|
$17,216 | $6,760 | ||
TOTAL IMPLEMENTED | $20,000 | $600 | - | - | $20,000 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs