ITAC Assessment: LM0039
ITAC logo
ITAC Assessment: LM0039
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product metal stampings
NAICS
n/a
SIC 3484: Small Arms
Sales Range $1
M
to 5
M
# of Employees 50
Plant Area 38,000
ft2
Annual Production 60,000,000
pieces
Production Hrs. Annual 2,600
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $55,662 539,958
kWh
Electricity Demand $32,413 3,996
kW-mo/yr
Electricity Fees $5,375 -
Natural Gas $4,993 515
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $40,037 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $20,000

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,575 $2,880 $1,228
10,264
kWh
$347
-
kW-mo/yr
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,338 $550 $3,773
31,542
kWh
$1,345
-
kW-mo/yr
$(-780.0) -
03 2.4221: Install compressor air intakes in coolest locations $211 $228 $161
1,350
kWh
$50
-
kW-mo/yr
- -
04 2.4231: Reduce the pressure of compressed air to the minimum required $1,154 - $883
7,378
kWh
$271
-
kW-mo/yr
- -
05 4.513: Re-arrange equipment layout to reduce labor costs $2,496 $900 - - $2,496 -
06 4.611: Begin a practice of predictive / preventative maintenance $20,000 $600 - - $20,000 -
07 4.454: Modify startup/shutdown times $10,263 $300 - $8,003
-
kW-mo/yr
$(-4,500.0) $6,760
TOTAL RECOMMENDED $40,037 $5,458 $6,045
50,534
kWh
$10,016
-
kW-mo/yr
$17,216 $6,760
TOTAL IMPLEMENTED $20,000 $600 - - $20,000 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs