Assessment Year | 2002 |
---|---|
Principal Product | envelopes |
NAICS |
n/a
|
SIC | 2677: Envelopes |
Sales Range | $10 M to 50M |
# of Employees | 166 |
Plant Area |
100,000
ft2
|
Annual Production | 2,300,000,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $444,811 | 5,373,576 |
kWh
|
$0.083 |
Electricity Demand | $158,235 | 35,076 |
kW-mo/yr
|
$4.51 |
Electricity Fees | $29,735 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $179,309 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $49,592 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $2,166 | $1,152 |
$1,758
15,506
kWh
|
$408
-
kW-mo/yr
|
- | - | |
02 | 2.7145: Install skylights | $6,152 | $4,400 |
$5,012
37,222
kWh
|
$1,140
-
kW-mo/yr
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $36,384 | $900 |
$30,071
265,244
kWh
|
$7,093
-
kW-mo/yr
|
$(-780.0) | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $494 | $250 |
$400
3,531
kWh
|
$94
-
kW-mo/yr
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,396 | - |
$3,558
31,385
kWh
|
$838
-
kW-mo/yr
|
- | - | |
06 | 4.321: Optimize production lot sizes and inventories | $66,667 | - | - | - | - | $66,667 | |
07 | 4.625: Develop standard operating procedures | $63,050 | $12,200 | - | - | $63,050 | - | |
TOTAL RECOMMENDED | $179,309 | $18,902 |
$40,799
352,888
kWh
|
$9,573
-
kW-mo/yr
|
$62,270 | $66,667 | ||
TOTAL IMPLEMENTED | $49,592 | $6,702 |
$40,799
352,888
kWh
|
$9,573
-
kW-mo/yr
|
$(-780.0) | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs