Assessment Year | 2004 |
---|---|
Principal Product | Oil field equipment |
NAICS | 333132: Oil and Gas Field Machinery and Equipment Manufacturing |
SIC | 3533: Oil and Gas Field Machinery and Equipment |
Sales Range | $1 M to 5M |
# of Employees | 30 |
Plant Area |
25,000
ft2
|
Annual Production | 1,200
pieces
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Louisiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $17,542 | 400,809 |
kWh
|
$0.044 |
Electricity Demand | $27,088 | 4,820 |
kW-mo/yr
|
$5.62 |
Electricity Fees | $3,437 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $26,171 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $24,732 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.6218: Turn off equipment when not in use | $19,102 | $30 |
$10,188
232,752
kWh
|
$7,548
-
kW-mo/yr
|
$1,366 | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,439 | $30 |
$1,336
30,530
kWh
|
- | $103 | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,042 | $2,920 |
$1,896
43,323
kWh
|
- | $146 | - | |
04 | 2.7111: Reduce illumination to minimum necessary levels | $1,020 | $990 |
$587
13,420
kWh
|
$360
-
kW-mo/yr
|
$73 | - | |
05 | 2.4222: Install adequate dryers on air lines to eliminate blowdown | $745 | $152 |
$692
15,812
kWh
|
- | $53 | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $323 | $245 |
$102
2,330
kWh
|
- | $8 | $213 | |
07 | 4.611: Begin a practice of predictive / preventative maintenance | $1,500 | $30 | - | - | - | $1,500 | |
TOTAL RECOMMENDED | $26,171 | $4,397 |
$14,801
338,167
kWh
|
$7,908
-
kW-mo/yr
|
$1,749 | $1,713 | ||
TOTAL IMPLEMENTED | $24,732 | $4,367 |
$13,465
307,637
kWh
|
$7,908
-
kW-mo/yr
|
$1,646 | $1,713 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs