ITAC Assessment: LL0181
ITAC logo
ITAC Assessment: LL0181
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Gas Compressors
NAICS 326122: Plastics Pipe and Pipe Fitting Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 90
Plant Area 50,000
ft2
Annual Production 200
pieces
Production Hrs. Annual 4,940
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $87,796 1,285,998
kWh
Electricity Fees $3,424 -
Natural Gas $37,085 3,472
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $15,081 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,903

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.7111: Reduce illumination to minimum necessary levels $3,934 $395 $3,786
55,462
kWh
$148 - -
02 2.2511: Insulate bare equipment $3,194 $1,013 - - $3,194
-
MMBtu
-
03 2.7261: Install timers and/or thermostats $2,927 $1,805 - - $2,927
-
MMBtu
-
04 2.7134: Use photocell controls $2,594 $420 $2,497
36,574
kWh
$97 - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,565 $1,015 $659
9,654
kWh
$26 - $880
06 2.7135: Install occupancy sensors $657 $135 $632
9,251
kWh
$25 - -
07 4.611: Begin a practice of predictive / preventative maintenance $210 $165 - - - $210
TOTAL RECOMMENDED $15,081 $4,948 $7,574
110,941
kWh
$296 $6,121
-
MMBtu
$1,090
TOTAL IMPLEMENTED $8,903 $2,588 $4,445
65,116
kWh
$174 $3,194
-
MMBtu
$1,090
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Fees Savings Natural Gas Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs