Assessment Year | 2003 |
---|---|
Principal Product | Gas Compressors |
NAICS | 326122: Plastics Pipe and Pipe Fitting Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 90 |
Plant Area |
50,000
ft2
|
Annual Production | 200
pieces
|
Production Hrs. Annual | 4,940
hrs
|
Location (State) | Louisiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $87,796 | 1,285,998 |
kWh
|
$0.068 |
Electricity Fees | $3,424 | - |
|
- |
Natural Gas | $37,085 | 3,472 |
MMBtu
|
$10.68 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $15,081 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,903 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7111: Reduce illumination to minimum necessary levels | $3,934 | $395 |
$3,786
55,462
kWh
|
$148 | - | - | |
02 | 2.2511: Insulate bare equipment | $3,194 | $1,013 | - | - |
$3,194
-
MMBtu
|
- | |
03 | 2.7261: Install timers and/or thermostats | $2,927 | $1,805 | - | - |
$2,927
-
MMBtu
|
- | |
04 | 2.7134: Use photocell controls | $2,594 | $420 |
$2,497
36,574
kWh
|
$97 | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,565 | $1,015 |
$659
9,654
kWh
|
$26 | - | $880 | |
06 | 2.7135: Install occupancy sensors | $657 | $135 |
$632
9,251
kWh
|
$25 | - | - | |
07 | 4.611: Begin a practice of predictive / preventative maintenance | $210 | $165 | - | - | - | $210 | |
TOTAL RECOMMENDED | $15,081 | $4,948 |
$7,574
110,941
kWh
|
$296 |
$6,121
-
MMBtu
|
$1,090 | ||
TOTAL IMPLEMENTED | $8,903 | $2,588 |
$4,445
65,116
kWh
|
$174 |
$3,194
-
MMBtu
|
$1,090 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs