Assessment Year | 1984 |
---|---|
Principal Product | YARN DYEING |
NAICS |
n/a
|
SIC | 2269: Finishers of Textiles, Not elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 16 |
Plant Area |
n/a
|
Annual Production | 4,000,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $143,438 | 2,994,138 |
kWh
|
$0.048 |
Natural Gas | $188,553 | 39,800 |
MMBtu
|
$4.74 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $34,787 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $29,619 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Natural Gas Savings |
---|---|---|---|---|---|
01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $6,815 | $200 |
$6,815
-
MMBtu
|
|
02 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $8,580 | $4,500 |
$8,580
-
MMBtu
|
|
03 | 2.2441: Preheat boiler makeup water with waste process heat | $14,224 | $9,000 |
$14,224
-
MMBtu
|
|
04 | 2.2511: Insulate bare equipment | $5,168 | $6,540 |
$5,168
-
MMBtu
|
|
TOTAL RECOMMENDED | $34,787 | $20,240 |
$34,787
-
MMBtu
|
||
TOTAL IMPLEMENTED | $29,619 | $13,700 |
$29,619
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs