| Assessment Year | 2002 |
|---|---|
| Principal Product | Rubber products |
| NAICS |
n/a
|
| SIC | 2822: Synthetic Rubber (Vulcanizable Elastomers) |
| Sales Range | $5 M to 10M |
| # of Employees | 60 |
| Plant Area |
97,000
ft2
|
| Annual Production | 3,000,000
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Louisiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $143,275 | 1,964,720 |
kWh
|
$0.073 |
| Electricity Fees | $5,331 | - |
|
- |
| Natural Gas | $33,841 | 2,885 |
MMBtu
|
$11.73 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $153,532 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,685 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7111: Reduce illumination to minimum necessary levels | $1,548 | - |
$1,488
20,405
kWh
|
$60 | - | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,068 | $210 |
$1,027
14,082
kWh
|
$41 | - | - | |
| 03 | 2.7135: Install occupancy sensors | $1,100 | $364 |
$1,058
14,511
kWh
|
$42 | - | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $450 | $90 |
$433
5,932
kWh
|
$17 | - | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $167 | $30 |
$161
2,213
kWh
|
$6 | - | - | |
| 06 | 4.446: Automate finishing process | $142,800 | $377,995 | - | - | - | $142,800 | |
| 07 | 3.5218: Reuse / recycle/ sell rubber products | $6,399 | - | - | - |
$6,399
-
lb
|
- | |
| TOTAL RECOMMENDED | $153,532 | $378,689 |
$4,167
57,143
kWh
|
$166 |
$6,399
-
lb
|
$142,800 | ||
| TOTAL IMPLEMENTED | $1,685 | $330 |
$1,621
22,227
kWh
|
$64 | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs