ITAC Assessment: LL0114
ITAC logo
ITAC Assessment: LL0114
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Fabricated Pipe
NAICS
n/a
SIC 3498: Fabricated Pipe and Pipe Fittings
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 4,200,000
ft2
Annual Production 200,000
pieces
Production Hrs. Annual 3,432
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $221,417 3,017,400
kWh
Electricity Demand $88,217 15,697
kW-mo/yr
Electricity Fees $(-34,141.0) -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,919 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,296

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings
01 2.7111: Reduce illumination to minimum necessary levels $745 - $356
6,638
kWh
$360
-
kW-mo/yr
$29 -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,623 $4,047 $1,492
27,784
kWh
$1,030
-
kW-mo/yr
$101 -
03 2.7134: Use photocell controls $1,539 $162 $1,096
14,820
kWh
$384
-
kW-mo/yr
$59 -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $628 $780 $603
8,166
kWh
- $25 -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,759 $2,340 $1,689
22,888
kWh
- $70 -
06 3.5313: Increase amount of waste recovered for resale $5,625 - - - - $5,625
-
lb
TOTAL RECOMMENDED $12,919 $7,329 $5,236
80,296
kWh
$1,774
-
kW-mo/yr
$284 $5,625
-
lb
TOTAL IMPLEMENTED $10,296 $3,282 $3,744
52,512
kWh
$744
-
kW-mo/yr
$183 $5,625
-
lb
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs