| Assessment Year | 2001 |
|---|---|
| Principal Product | Metal Doors and Windows |
| NAICS |
n/a
|
| SIC | 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
125,000
ft2
|
| Annual Production | 235,000
pieces
|
| Production Hrs. Annual | 2,250
hrs
|
| Location (State) | Louisiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $51,814 | 694,601 |
kWh
|
$0.075 |
| Electricity Demand | $15,640 | 2,995 |
kW-mo/yr
|
$5.22 |
| Electricity Fees | $(-8,759.0) | - |
|
- |
| Natural Gas | $11,300 | 1,364 |
MMBtu
|
$8.28 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $17,282 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $290 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $290 | $432 |
$323
9,715
kWh
|
- | $11 |
$(-44.0)
-
MMBtu
|
- | - | |
| 02 | 2.7135: Install occupancy sensors | $2,969 | $4,650 | - |
$2,855
-
kW-mo/yr
|
$114 | - | - | - | |
| 03 | 2.4226: Use / purchase optimum sized compressor | $5,564 | $27,000 |
$3,589
120,598
kWh
|
$1,761
-
kW-mo/yr
|
$214 | - | - | - | |
| 04 | 2.8114: Change rate schedules or other changes in utility service | $5,316 | $1,000 | - | - | - | - | - | $5,316 | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,810 | $4,752 |
$1,110
26,550
kWh
|
$1,592
-
kW-mo/yr
|
$108 | - | - | - | |
| 06 | 3.5313: Increase amount of waste recovered for resale | $333 | - | - | - | - | - |
$333
-
lb
|
- | |
| TOTAL RECOMMENDED | $17,282 | $37,834 |
$5,022
156,863
kWh
|
$6,208
-
kW-mo/yr
|
$447 |
$(-44.0)
-
MMBtu
|
$333
-
lb
|
$5,316 | ||
| TOTAL IMPLEMENTED | $290 | $432 |
$323
9,715
kWh
|
- | $11 |
$(-44.0)
-
MMBtu
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs