ITAC Assessment: LL0110
ITAC logo
ITAC Assessment: LL0110
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Metal Doors and Windows
NAICS
n/a
SIC 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 125,000
ft2
Annual Production 235,000
pieces
Production Hrs. Annual 2,250
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $51,814 694,601
kWh
Electricity Demand $15,640 2,995
kW-mo/yr
Electricity Fees $(-8,759.0) -
Natural Gas $11,300 1,364
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,282 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $290

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Solid Waste (non-haz) Savings Primary Product Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $290 $432 $323
9,715
kWh
- $11 $(-44.0)
-
MMBtu
- -
02 2.7135: Install occupancy sensors $2,969 $4,650 - $2,855
-
kW-mo/yr
$114 - - -
03 2.4226: Use / purchase optimum sized compressor $5,564 $27,000 $3,589
120,598
kWh
$1,761
-
kW-mo/yr
$214 - - -
04 2.8114: Change rate schedules or other changes in utility service $5,316 $1,000 - - - - - $5,316
05 2.7142: Utilize higher efficiency lamps and/or ballasts $2,810 $4,752 $1,110
26,550
kWh
$1,592
-
kW-mo/yr
$108 - - -
06 3.5313: Increase amount of waste recovered for resale $333 - - - - - $333
-
lb
-
TOTAL RECOMMENDED $17,282 $37,834 $5,022
156,863
kWh
$6,208
-
kW-mo/yr
$447 $(-44.0)
-
MMBtu
$333
-
lb
$5,316
TOTAL IMPLEMENTED $290 $432 $323
9,715
kWh
- $11 $(-44.0)
-
MMBtu
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Solid Waste (non-haz) Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs