ITAC Assessment: LE0609
ITAC logo
ITAC Assessment: LE0609
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Asphalt
NAICS 324121: Asphalt Paving Mixture and Block Manufacturing
SIC 2951: Asphalt Paving Mixtures and Blocks
Sales Range $10
M
to 50
M
# of Employees 15
Plant Area 62,500
ft2
Annual Production 300,000
ton
Production Hrs. Annual 2,640
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $496,406 8,279,648
kWh
Electricity Demand $614,562 58,906
kW-mo/yr
Natural Gas $539,000 146,836
MMBtu
TOTAL YEARLY COSTS $1,649,968
RECOMMENDED SAVINGS* $99,940 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $17,125 $2,840 $13,975
232,843
kWh
$3,150
-
kW-mo/yr
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $14,372 $2,598 $14,372
239,527
kWh
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $37,996 $12,500 $21,225
353,760
kWh
$16,771
-
kW-mo/yr
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $20,137 $11,000 $11,246
187,440
kWh
$8,891
-
kW-mo/yr
05 2.4112: Install soft-start to eliminate nuisance trips $1,627 $2,000 - $1,627
-
kW-mo/yr
06 2.4226: Use / purchase optimum sized compressor $7,089 $15,050 $3,960
66,000
kWh
$3,129
-
kW-mo/yr
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,594 $8,000 $1,406
23,436
kWh
$188
-
kW-mo/yr
TOTAL RECOMMENDED $99,940 $53,988 $66,184
1,103,006
kWh
$33,756
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs